Scope of the Phase 2 of the project is to provide additional technical assistance that will
address the variation of fixed and variable costs and continue data collection efforts of generator-level
commercial data to develop cost-based pricing of ancillary services and balancing services within each
Black Sea partner country.
Grid Connection & Grid Code Compliance Studies for 144 MWh Pasewalk BESS Project

- Client: Intec
- Country: Germany
- Year: Aug, 2026