Grid Code Compliance Tests of 240 MW Khizi & Absheron Wind Power Project in Azerbaijan

Following grid-code compliance tests on-site will be performed to check whether the turbines and power plant controller of the powerplant satisfy the requirements defined in the Azerbaijan Grid Code:

  • Pre-Test Planning and Coordination
  • Fault Ride Through (FRT) Parameter Verification
  • Active Power and Frequency Control Tests
  • Reactive Power and Voltage Control Capability Tests
  • Power Quality Measurement and Analysis