Grid Connection, Grid Code Compliance & Power Quality Impact Analyses of 100 MW Gobustan Solar PV Project in Azerbaijan

Scope of the project includes the following studies:
Grid Code Compliance Analyses of 40 MW Lachendorf PV Solar Power Plant – Germany

Scope of the project includes the following studies:
Grid Code Compliance Tests of 240 MW Khizi & Absheron Wind Power Project in Azerbaijan

Following grid-code compliance tests on-site will be performed to check whether the turbines and power plant controller of the powerplant satisfy the requirements defined in the Azerbaijan Grid Code:
42 MW Alparslan2 Hybrid Power Plant (HPP & SPP) – Grid Code Compliance Analysis

Grid code compliance studies include:
Bandırma RES 6 MW Enercon E-175 EP5 turbine grid connection & compatibility analysis

Grid Connection & Grid Code Compliance Analyses of MEGA Solar PV Projects in Azerbaijan

Grid Connection & Grid Code Compliance Analyses of Mega Solar PV Projects in Azerbaijan: The analyses include the following studies for both mega PV solar projects: Grid code compliance of MEGA renewable projects is important for the secure and reliable transition of power grids. We are happy to contribute such a secure and reliable transition […]
Grid Connection Analyses of 240 MW Sunrise PV Solar Power Plant in Azerbaijan

Scope of the project includes the following studies:
94 MW Cemre Battery Storage Solar Power Plant – Grid Code Compliance Analysis

Grid code compliance studies include: In addition, layout optimization and technical loss analysis will be performed in the scope of the project.
LVRT & Frequency Control Analysis of 230 MW Garadagh – Solar Power Plant

The study, which will be performed with DIgSILENT PowerFactory, will investigate Low Voltage Ride Through (LVRT) and Frequency Control (FC) capabilities of the Solar Power Plant in terms of the Azerbaijan Grid Code and Power Purchase Agreement (PPA) of the plant.
Grid Code Compliance Analysis 240 MW Khizi – Absheron Wind Power Project

Grid code compliance studies include: